Mostly the product backlog will have many items falling under Mo (Must Be) and S (Should Be) of MoSCoW. How will you prioritize within these items? |
|
Answer» MoSCoW is a very BASIC PRIORITISATION technique. Most of the PBI will be falling under Mo and S. An experienced PO would be using various other WAYS to differentiate between Mo and S. POPULAR one is WSJF – Weighted Shortest Job First. WSJF = Cost Of Delay / Job SIZE. |
|