P can finish a piece of work in 30 dayswhile Q can finish it in 40 days. In howmany days can P and Q workingtogether finish it? |
|
Answer» P can finish a work in 30 days so 1/30Q can finish a work in 40 days so 1/40so if both will work together then 1/30+1/40=(4+3)/120so in 120/7 days they will complete the work |
|