Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using the shortest processing time rule is ___ (correct two decimal places). Job Processing time (days) Due date (days) A 3 8 B 7 16 C 4 4 D 9 18 E 5 17 F 13 19 6.33

Answer» Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using the shortest processing time rule is ___ (correct two decimal places).








































Job Processing time (days) Due date (days)
A 3 8
B 7 16
C 4 4
D 9 18
E 5 17
F 13 19


  1. 6.33