Size of the kiln needed to manufacture the cement is bigger for wet process.(a) True(b) FalseThe question was posed to me in quiz.My enquiry is from Wet Process in division Cement of Concrete Technology

Answer»

Correct choice is (a) True

The explanation is: The kiln SIZE is BIGGER for WET process than for DRY process to manufacture the CEMENT because much of the kiln’s length was used up for the drying process.