1.

Survey stations may be marked on the ground using a:(a) Pole(b) Rod(c) Pointer(d) PegI have been asked this question in an online interview.The query is from Chain Surveying in portion Basic Surveying of Basic Civil Engineering

Answer»

The correct answer is (d) Peg

The EXPLANATION is: Peg is a wooden BLOCK with a POINTED edge to drive it into the GROUND. They are generally 2.5-3 cm^2 and 15cm LONG, with tapered end.