1.

The are 16 workers working to construct a wall and it will take 48 hours to build it. But due to some accident, 4 workers got injured and could not work. Now, the contractor wants the wall to be built in 32 hours. How many more workers are required to complete the job?

Answer»

The are 16 workers working to construct a wall and it will take 48 hours to build it. But due to some accident, 4 workers got injured and could not work. Now, the contractor wants the wall to be built in 32 hours. How many more workers are required to complete the job?




Discussion

No Comment Found

Related InterviewSolutions