The concrete is contained in a timber or steel casing for a certain period after its placing, this casing is known as the ____________(a) Tremie(b) Hopper(c) Shuttering(d) GroutingThis question was posed to me in an online interview.I would like to ask this question from Placing of Concrete topic in section Cement Concrete Construction of Construction & Building Materials

Answer»

The correct option is (C) Shuttering

To elaborate: The shuttering, formwork or moulds is to be REMOVED when CONCRETE has Harden sufficiently to support its own weight. The formwork should be designed in such a way that it can be EASILY removed and used again.