1.

The expected out turn for earth work in excavation in ordinary soil per labourer per day is _____(a) 1 cum(b) 2 cum(c) 3 cum(d) 4 cum

Answer» Right answer is (c) 3 cum

Explanation: Sand = 4 cum

Ordinary soil = 3 cum

Compacted soil = 2 cum

Rock = 1 cum.