| 1. |
The expected out turn for earth work in excavation in ordinary soil per labourer per day is _____(a) 1 cum(b) 2 cum(c) 3 cum(d) 4 cum |
|
Answer» Right answer is (c) 3 cum Explanation: Sand = 4 cum Ordinary soil = 3 cum Compacted soil = 2 cum Rock = 1 cum. |
|