1.

The expected out turn of 2.5 cm cement concrete floor per mason per day _____________(a) 2.5 sqm(b) 5.0 sqm(c) 7.5 sqm(d) 10 sqm

Answer» Correct option is (c) 7.5 sqm

To elaborate: For 100 sum, no. of Mason is 13 no. i.e. for 13 Mason flooring is 100 square meter.

So for 1 Mason flooring is 100/13 = 7.69 sum.

So option 7.5 sqm is the answer.


Discussion

No Comment Found

Related InterviewSolutions