Saved Bookmarks
| 1. |
The expected out turn of 2.5 cm cement concrete floor per manson per day?(a) 1.5 sq. m(b) 0.5 sq. m(c) 7.5 sq. m(d) 2.5 sq. m |
|
Answer» Correct answer is (c) 7.5 sq. m The explanation is: For 100 sum, no. of Mason is 13 no. i.e for 13 Mason flooring is 100 square meter. So for 1 Mason flooring is 100/13 = 7.69 sum. |
|