1.

The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to complete the project using the effort formula of basic COCOMO given below :E = a(KLOC)bAssume that the values of a and b are 2.5 and 1.0 respectively.(A) 25 person months(B) 75 person months(C) 62.5 person months(D) 72.5 person months

Answer»