1.

The rates of materials used for government works are approved by _________(a) Executive Board(b) SDO(c) Elective Board(d) Board of Chief EngineersThis question was addressed to me during an interview.The doubt is from Labour and Rate Analysis topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials

Answer»

Correct CHOICE is (d) Board of Chief Engineers

For explanation I WOULD say: The Board of Chief Engineers approves the rates of MATERIALS USED for government works. However, every year, these are fixed by the Superintendent ENGINEER.