The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them to finish the work are in the ratio A. 3 : 4 B. 9 16 C. 4: 3 D. 16 : 9 |
|
Answer» We know that number of days taken to work is reciprocal of the rate of the work. ∴ Work done by A: \(\frac{1}{3}\) Work done by B: \(\frac{1}{4}\) ∴ Ratio of work done is \(\frac{1}{3}:\frac{1}{4}=4:3\) |
|