| 1. |
Two women were going to be paid Rs 3200. Woman 1 can complete a piece of work in 10 days, second can complete in 8 days. Now when a man joins them, the work gets completed in 3 days. Calculate share of man. 1. Rs 10752. Rs 10403. Rs 14004. Rs 15005. Rs 1600 |
|
Answer» Correct Answer - Option 2 : Rs 1040 Given: Woman 1 = 10 days 2 woman + 1 man = 3 days Formula used: 1/T = (1/T1) + (1/T2) Here, T1 = work done in days by 1, T2 = work done in days by 2 Calculation: Let’s calculate total number of units in form of work done ⇒ LCM of 10, 8, 3 is 120 ⇒ Efficiency of woman 1 = (120/10) ⇒ Efficiency of woman 1 = 12 ⇒ Efficiency of woman 2 = 15 (∵ 120/8 = 15) ⇒ Efficiency of 2 woman + Man = 40 (∵ 120/3 = 40) Now, Efficiency of man ⇒ Efficiency of man = Total efficiency – Efficiency of 2 women ⇒ Efficiency of man = 40 – 27 ⇒ Efficiency of man = 13 For, Total work done wage to be paid was Rs 3200 ⇒ for 40 units of work wage = 3200 ⇒ For 13 units of work, wage = 3200 × 13/40 ⇒ Wage to be paid to man = 80 × 13 ∴ Man will be paid Rs 1040 |
|