What are the basic performance reports which will be prepared by the team? |
|
Answer» KNOWLEDGE Area: Integration MANAGEMENT Corrective action is to correct the existing variance. PREVENTIVE action is to ensure that similar current variances should not occur in future. For example, if we identify that the project is running behind schedule, then the corrective action will be SOMETHING that can help to expedite the remaining WORK so that we can make up the schedule variance. After doing a root cause analysis, if the team realizes that the schedule variance happened because of lack of clear management direction to the team, then the preventive action will include providing clear direction and information to each team member for their corresponding work so that similar variances will not occur in future. |
|