What information is required to process a change to a baseline?(a) Reasons for making the changes(b) A description of the proposed changes(c) List of other items affected by the changes(d) All of the mentionedI got this question during an interview.This interesting question is from Software Control in division Software Testing and Quality Management of Software Engineering

Answer»

The CORRECT ANSWER is (d) All of the mentioned

For explanation I would say: A baseline is an agreed-to description of the PRODUCT, changes REQUIRE multiple reasons..