What Is A Constraint In Primavera?

Answer»

Constraints in primavera is to FIX the start or finish DATE as per FOLLOWING OPTIONS:

  1. Project Must Finish byandatory Start / Mandatory Finish
  2. Start / Finish On or After
  3. Start / Finish On or Before
  4. Start / Finish On
  5. Expected Finish

Constraints in primavera is to fix the start or finish date as per following options: