What Is Planning Strategy You Select To Perform Mts And Mto? |
|
Answer» When you USE Planning strategy 10, only PIR quantity is considered for MRP run and sales order are completely IGNORED. In this PIR requirement type LSF and is reduced when you deliver stock to customer. You use Planning strategy 20 for make to order MTO process and planning strategy 25 is used to produce product variants when there is request for VARIANT products from customer. When you use Planning strategy 10, only PIR quantity is considered for MRP run and sales order are completely ignored. In this PIR requirement type LSF and is reduced when you deliver stock to customer. You use Planning strategy 20 for make to order MTO process and planning strategy 25 is used to produce product variants when there is request for variant products from customer. |
|