1.

What Is The Difference Between Pp And Pp-pi? Which One Is Better And How ?

Answer»
  •  PP--> Production PLANNING mostly used for discrete type of industries, where at the time of confirmation the output is sure to be fixed.
  • eg AUTOMOBILE

  • PP- PI--> Production Planning for Process Industries , here mostly used for the typical chemical industries , as the Yield is not fixed due to chemical reaction yield values can be varied to NOTICEABLE EXTENT.
  • Eg X+Y =Z some 10 kg of X and 1 KG of Y gives yield that is Z of 10 Kg only.

eg Automobile

Eg X+Y =Z some 10 kg of X and 1 KG of Y gives yield that is Z of 10 Kg only.