What is the methodology for arriving at the labour budget estimate? |
|
Answer» The LB estimate under MGNREGA is based on the amount of total cost (viz. cost towards wage, material and administrative costs) to be incurred while generating a personday wage employment. The expenditure per personday generation of wage employment shall have wage and material costs in the proportion of 60:40. For example, if the cost of the project is Rs. 100, the wage expenditure is at least Rs.60 and the material expenditure is at most Rs. 40. Further, a maximum of Rs. 6 can be utilised towards administrative expenses over and above the wage and material expenses. |
|