What is the recommended distribution of effort for a project?(a) 40-20-40(b) 50-20-30(c) 30-40-30(d) 50-30-20I got this question at a job interview.Enquiry is from Project Scheduling and Tracking in section Software Management of Software Engineering

Answer»

Correct choice is (a) 40-20-40

Explanation: A recommended distribution of effort across the SOFTWARE process is 40% (ANALYSIS and DESIGN), 20% (coding), and 40% (TESTING)‏.