Which model is used during early stages of the system design after the requirements have been established?(a) An application-composition model(b) A post-architecture model(c) A reuse model(d) An early design modelI had been asked this question in an interview.This interesting question is from Size and Cost Estimation of Software topic in chapter Software Management of Software Engineering

Answer»

Correct option is (d) An early design model

Explanation: Estimates are BASED on function points, which are then converted to number of lines of source CODE. The formula follows the standard form discussed above with a SIMPLIFIED set of SEVEN MULTIPLIERS.