Which of the following does not apply to agility to a software process?(a) Uses incremental product delivery strategy(b) Only essential work products are produced(c) Eliminate the use of project planning and testing(d) All of the mentionedThis question was addressed to me in an online quiz.My enquiry is from Agile Software Development topic in portion Software Processes, Models and Agile Software Development of Software Engineering |
|
Answer» The correct CHOICE is (c) Eliminate the use of project planning and testing |
|