| 1. |
Which of the following is not a change management process?(a) Log the changes(b) Estimate impact on effort and schedule(c) Review impact with stakeholders(d) None of the mentionedI got this question by my school teacher while I was bunking the class.My doubt is from Software Control topic in portion Software Testing and Quality Management of Software Engineering |
|
Answer» RIGHT choice is (d) NONE of the mentioned Best EXPLANATION: All are required for a change. |
|