1.

Which of the following is not an adaptation criteria for software projects?(a) Size of the project(b) Customers Complaints(c) Project staff(d) Mission criticalityI got this question in an international level competition.Query is from Project Scheduling and Tracking in section Software Management of Software Engineering

Answer»

Right CHOICE is (b) CUSTOMERS Complaints

Easy explanation: These can VARY from CLIENT to client.