1.

Which of the following is not considered as a risk in project management?(a) Specification delays(b) Product competition(c) Testing(d) Staff turnoverThe question was posed to me during an online interview.My query is from Project Management topic in chapter Software Management of Software Engineering

Answer»

The correct answer is (c) Testing

Explanation: Testing is a PART of PROJECT, THUS it can’t be categorized as RISK.