1.

Which of the following must be done before operating a crane?Select all that apply.A.)Barricading areas within the swing radiusB.)Contacting power line ownersC.)Leveling the craneD.)Making other personnel aware of hoisting activities

Answer»

EXPLANATION:

LEVELLING the crane

follow me.