1.

Which of the following states that work expands to fill the time available.(a) CASE tools(b) Pricing to win(c) Parkinson’s Law(d) Expert judgementI have been asked this question during an interview.My doubt is from Size and Cost Estimation of Software in division Software Management of Software Engineering

Answer»

Right option is (c) Parkinson’s Law

To explain: The cost is determined by available resources rather than by objective assessment. If the SOFTWARE has to be DELIVERED in 12 MONTHS and 5 people are available, the effort required is estimated to be 60 person-months.