1.

Which of the following uses empirically derived formulas to predict effort as a function of LOC or FP?(a) FP-Based Estimation(b) Process-Based Estimation(c) COCOMO(d) Both FP-Based Estimation and COCOMOThis question was posed to me in my homework.My enquiry is from Empirical Estimation Models topic in portion Software Management of Software Engineering

Answer»

The CORRECT OPTION is (d) Both FP-Based ESTIMATION and COCOMO

The explanation: Function points and COCOMO are used to evaluate effort.