1.

Which one of the following is not a part of pug mill?(a) Vertical shaft(b) Hub(c) Cutting blades(d) Timber baseThe question was asked during an interview.The above asked question is from Manufacture of Brick in section Materials for Construction of Basic Civil Engineering

Answer» RIGHT choice is (b) Hub

For explanation I would say: Hub is a part of KAPLAN turbine.Pub mill is where pugging is CARRIED out.It consists of a conical iron tub, cutting blades, vertical SHAFT, horizontal arm, long wooden arm and TIMBER base.