1.

Which software project sizing approach develop estimates of the information domain characteristics?(a) Function point sizing(b) Change sizing(c) Standard component sizing(d) Fuzzy logic sizingI got this question in class test.I'd like to ask this question from Decomposition Techniques in Software Project Planning topic in portion Software Management of Software Engineering

Answer»

The correct answer is (a) FUNCTION POINT sizing

To EXPLAIN: None.



Discussion

No Comment Found

Related InterviewSolutions