1.

Which technique is applicable when other projects in the same analogy application domain have been completed?(a) Algorithmic cost modelling(b) Expert judgement(c) Estimation by analogy(d) Parkinson’s LawI got this question in an interview.The question is from Size and Cost Estimation of Software topic in section Software Management of Software Engineering

Answer»

Correct option is (C) ESTIMATION by ANALOGY

The EXPLANATION is: The cost of a new project is estimated by analogy with these completed projects.