Working together B and C take 50% more number of days than A,B and C together take and A and B working together, take 8/3 more number of days than A, B and C take together. If A, B and C all have worked together till the completion of the work and B has received ₹ 120 out of the total earning of ₹ 450, then in how many days did A, B and C together complete the whole work? |
|
Answer» 10 |
|