Working together, P and Q can do a job in 6 days, Q and R can do the same job in 10 days while P and R can do it in 5 days How long will it take, if all of them work together to complete the job?

Answer»

`4 (2)/(7)` DAYS
`4(3)/(7)` days
`4(4)/(7)` days
`4(5)/(7)` days

Answer :A