X and Y finish a work in the same time as Z alone. X can alone finish the work in 30 days, Z can alone finish work in 16 days. In how many days Y alone finishes the work?1. 34.22. 39.83. 36.44. 31.4 |
|
Answer» Correct Answer - Option 1 : 34.2 Given: X and Y finish a work in the same time as Z alone. X can alone finish the work in 30 days. Z can alone finish work in 16 days. Formula Used: If A and B can together finish a work in t days and alone can finish the work in a and b days respectively, Then, 1/a + 1/b = 1/t Work = Time × Efficiency Calculation: Total work = LCM of 30 and 16 = 240 units Efficiency of X = 240/30 = 8 Efficiency of Z = 240/16 = 15 Combined efficiency of x + y = 15 (as X and Y finish a work in the same time as Z alone) ⇒ 8 + y = 15 ⇒ Y = 7 Time taken by Y = 240/7 days = 34.2 days ∴ Y alone finishes the work in 34.2 days. |
|