10 women can complete a work in 8 days and 10 children take 12 days to complete the work. How many days will 6 women and 3 children together take to complete the work?1). 92). 123). 74). 8 |
|
Answer» Solution 10 WOMEN can complete the work in 8 days. So, NUMBER of hours required for 1 woman to complete the work = 80 Number of hours required by one child to complete the work = 120 So, 80W = 120C => 1W = 1.5C 6 women + 3 children = 9 children + 3 children = 12 children So, 12 children take 10 days to complete the work. |
|