11. 25 men working 8 hours a day do a job in 63 days. How long would 45 men take to finish the job, working 7 hours a day?​

Answer»

\large{\underline{\rm{\blue{\bf{Question:-}}}}}

25 men WORKING 8 hours a day do a job in 63 days. How long would 45 men take to finish the job, working 7 hours a day?

\large{\underline{\rm{\blue{\bf{Given:-}}}}}

Days taken by ​25 men working 8 hours a day do a job = 63 hours

\large{\underline{\rm{\blue{\bf{To \: Find:-}}}}}

Days taken if 45 men take to finish the job, working 7 hours a day.

\large{\underline{\rm{\blue{\bf{Solution:-}}}}}

According to the question,

TIME taken by 25 men to complete the work = \sf 8 \times 63 = 504 \: hours

Then,

Time taken by 1 men to complete the work = \sf 25 \times 504 = 12600 \: hours

Then, finding

Time taken by 45 men to complete the work = \sf \dfrac{12600}{45} = 280 \: hours

Therefore,

Time taken by 45 men to complete the work, working 7 hours a day = \sf \dfrac{280}{7}=<klux>40</klux> \: days

HENCE, 40 days are taken by 45 men to complete the work, working 7 hours a day.