12 men working at 6 hours for that can do a piece of work in 14 days how many workers can complete the same work in 8 days working at this per day |
|
Answer» 12:x=7x4:6x7 12:x=4:6 12:x=2:3 2xx=12x3 2x=36 x=36 by 2 x=18 number of REQUIRED WORKERS = 18 |
|