19. A certain number of men complete a piece of work in 60 days. If there were8 men more, the work could be finishedin 10 days less. How many men wereoriginally there?(A) 30[B] 32[C] 36[D] 40 |
|
Answer» D 40Step-by-step EXPLANATION:LET X men can do a work in 60 days and similarly (x+8) men can do a work in 50 days .==> 60x=50(x+8)==>10x=400==>x=40 |
|