2 women and 10 children together take 8 days to complete a piece of work How many days will 10 children alone take to complete the piece of work if 8 women alone can complete the piece of work in 6 days ?1). 152). 123). 104). 24

Answer»

Solution

LET the speed of WOMEN be x and that of children be y. Let the PIECE of work be W.
2x + 10Y = W/8
8x = W/6
x = W/48
Hence, we get y= W/120
Speed of 1 CHILD = W/120
Speed of 10 children = W/12
Now time needed for them to complete = W/(W/12) =12days
Therefore, the correct option is B.