40 workers working for 8 hours per day digs a hole of 1088 m3. If 45 workers work for 6 hours a day, then what volume of the hole they can dig in m3?918

Answer» 40 workers working for 8 hours per day digs a hole of 1088 m3. If 45 workers work for 6 hours a day, then what volume of the hole they can dig in m3?
  1. 918