Saved Bookmarks
| 1. |
45 men complete a work in 15 day. if 30 men join them, how many days will they take to complete the work? |
|
Answer» 9 daysStep-by-step explanation:TOTAL WORK by 45 men in 15 DAYS is 45×15 man daysif 30 men are added total men is 75 and NUMBER of days be 'X'as work is same45×15=30×XX=9 |
|