5. A contractor employs 360 men who can finish a certain piece of work in 11 months. How many moremen must be employed to complete the work in 9 months? please send me picture solution please |
|
Answer» now... if11months - 360men9months - (?)by INVERSE proportion11*360/9 = 440men |
|