5. Malini can do a piece of work in 20 days, whereasShalini can do it in 25 days. Shalini started the workand after 5 days, Malini joined her. They togethercompleted the remaining work. How many daysdid they take to complete the whole work?1(a) 8(b) 88.(c) 88(d) 1399 |
|
Answer» Answer: Options are incorrect but answer in approx is 13 days Let total work is 100 Efficiency of MALINI = 100/20 = 5 Work/ day Efficiency of Shalini = 100/25 = 4 Work/ day Shalini START work and did for 5 days Work DONE in 5 days = 4 X 5 = 20 work Work left = 100-20 = 80 work Now, they start doing work together So, 80/9 So, Now total days 4 + 80/9 116/9 days or or 13 days (approx) HOPE IT HELPS |
|