6 men can complete a job in 15 days. How many men should work, if the job is to becompleted in 10 days? |
|
Answer» Answer: 15 DAYS is TAKEN to complete the work by=6 men 1 DAY will be TAKE to complete the work by=6/15 men then, the no of men complete it in 10 days =6/15*10 =4MEN answer plz mark the answer brainlist |
|