8 Children And 12 Men Complete A Certain Piece Of Work In 9 Days. If Each Child Takes Twice The Time Taken By Man To Finish The Work. In How Many Days Will 12 Men Finish The Same Work? |
|
Answer» 2 children = 1 man THEREFORE (8 children +12 MEN) = 16 men Now less men more days 12: 16 : : 9 : X Therefore, x = (144/12) = 12 days. 2 children = 1 man Therefore (8 children +12 men) = 16 men Now less men more days 12: 16 : : 9 : x Therefore, x = (144/12) = 12 days. |
|