| 1. |
90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working 712 hours a day? |
|
Answer» 90 men can complete a work in 24 days working 8 hours a day. How many men are required to complete the same work in 18 days working 712 hours a day? |
|