A and B can do a piece of work, in 15 days and 20 days respectivelyFind (i) The work done by A in 3 days (ii) The work left after A has worked for 3 days.(iii) The number of days that B will take to complete the remaining work. |
|
Answer» Step-by-step explanation: R.E.F image A→ 20 days B→ 15 days Let US SAY. 60 unit work was there & C = x unit/DAY. A = 3 unit/Day B=4 unit /Day. A+B = 7×6=42 unit work done by A & B. LEFT (60-42) unit = 10 unit will be done by A&C A+C=(3+x)×4=10⇒12+4x=10⇒x= 4 6 =2.5 day unit . C Alone could do the work. = 1.5unit/day 6.0unit = 40 day |
|