A and B can do a piece of work, in 15 days and 20 days respectivelyFind (i) The work done by A in 3 days (ii) The work left after A has worked for 3 days.(iii) The number of days that B will take to complete the remaining work.​

Answer»

Step-by-step explanation:

R.E.F image

A→ 20 days

B→ 15 days

Let US SAY. 60 unit work was there & C = x unit/DAY.

A = 3 unit/Day

B=4 unit /Day.

A+B = 7×6=42 unit work done by A & B. LEFT

(60-42) unit = 10 unit will be done by A&C

A+C=(3+x)×4=10⇒12+4x=10⇒x=

4

6

=2.5

day

unit

.

C Alone could do the work.

=

1.5unit/day

6.0unit

= 40 day