a and b can do a piece of work in 6 days,b in 8 days and c in 4 days. if all work together, how much money should each receive? |
|
Answer» Answer: A should get 1/24 the MONEY while b and c should get 1/8 and 1/4 money respectively Step-by-step EXPLANATION: It is CALCULATED from the reciprocal of days TAKEN to finish the WORK Hence, Work done by A = |
|