A' And 'b' Complete A Work Together In 8 Days.if 'a' Alone Can Do It In 12 Days.then How Many Day 'b' Will Take To Complete The Work? |
|
Answer» A & B one day work = 1/8 A ALONE one day work = 1/12 B alone one day work = (1/8 - 1/12) = ( 3/24 - 2/24) => B one day work = 1/24 so B can complete the work in 24 DAYS. A & B one day work = 1/8 A alone one day work = 1/12 B alone one day work = (1/8 - 1/12) = ( 3/24 - 2/24) => B one day work = 1/24 so B can complete the work in 24 days. |
|